Electrical infrastructure for a 20 MW industrial facility in Portuguesa
This case reflects the founding team’s prior experience, gained outside Orinoco Energy Solutions. It is not an Orinoco corporate contract.
Orinoco’s founding team took part in the electrical infrastructure of a 20 MW industrial facility in Portuguesa state. The scope covered the 13.8 kV feeder, transformation to 480 V and the site’s low-voltage distribution.
Key data
| Location | Portuguesa state, Venezuela |
|---|---|
| Site capacity | 20 MW (facility capacity, not installed generation) |
| Medium voltage | 13.8 kV feeder |
| Low voltage | Transformation to 480 V and distribution |
Described scope
- Feeder
- Dedicated at 13.8 kV, interconnected to the substation.
- Transformation
- Power 13.8 kV → 480 V.
- Distribution
- Main panels and low-voltage systems.
- Infrastructure
- Industrial grounding and full commissioning.
This case is one of the 8 energized facilities the team took part in, across five Venezuelan states.
Contact
Let’s discuss your electrical infrastructure.
Share the location, assets or systems involved, required scope and target date. For maintenance, please include site access conditions and the available work window.
info@orinocoenergy.net Orinoco Energy Solutions, C.A. · Venezuela
Infrastructure for operations that cannot stop.